Report Title:
CIP; South and West Maui
Description:
Issues general obligation bonds for various CIP projects in South and West Maui.
THE SENATE |
S.B. NO. |
1551 |
TWENTY-SECOND LEGISLATURE, 2003 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
AUTHORIZING THE ISSUANCE OF GENERAL OBLIGATION BONDS FOR THE FIFTH SENATORIAL DISTRICT.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The director of finance is authorized to issue general obligation bonds in the sum of $ , or so much thereof as shall be sufficient in fiscal years 2003-2004, and 2004-2005, to finance the following South and West Maui capital improvement projects:
(1) Lahainaluna high school, Maui
Replacement of Building D
Planning and design $ 200,000
Construction 2,400,000
(2) Lahainaluna high school, Maui
Replacement of existing cafetorium
Planning and design $ 250,000
Construction 4,000,000
(3) Lahainaluna high school, Maui
Drainage engineering for water runoff
Planning, design and construction $16,000,000
(4) Lahaina intermediate school, Maui
Planning, design and construction of a new administration/library building
Planning and design $ 350,000
Construction 3,550,000
Equipment 100,000
(5) Lahaina intermediate school, Maui
Planning, design and construction of a new 8-classroom building
Planning and design $ 300,000
Construction 2,600,000
Equipment 100,000
(6) Lahaina intermediate school, Maui
Drainage engineering for water runoff
Planning, design and construction $ 2,000,000
(7) Princess Nahienaena school, Maui
Planning, design and construction of a new library building
Planning, design and construction $ 800,000
(8) Princess Nahienaena school, Maui
Drainage engineering for water runoff
Planning, design and construction $ 2,000,000
(9) Kihei high school, Maui
Planning, design and construction of a new high school for the Kihei community
Land acquisition, planning, design and construction $55,000,000
(10) Lokelani middle school, Maui
Planning, design and construction of a new 6-classroom building
Planning and design $ 260,000
Construction 2,500,000
Equipment 100,000
(11) Lokelani middle school, Maui
Planning, design and construction of a new 2-classroom portable library building
Planning, design and construction $ 500,000
(12) Lokelani middle school, Maui
Planning, design and construction of an administration building
Planning, design, construction and equipment $ 3,630,000
(13) Lokelani middle school, Maui
Planning, design and construction of a new library
Planning, design, construction and equipment $ 2,400,000
(14) Kihei elementary school, Maui
Planning, design and construction of a new library
Planning, design, construction and equipment $ 2,000,000
(15) Kihei elementary school, Maui
Planning, design and construction of a new administration building
Planning, design, construction and equipment $ 2,385,000
(16) King Kamehameha III school, Maui
Repair of sea wall for safety reasons
Planning, design, and construction $ 350,000
(17) King Kamehameha III school, Maui
Replacement of louvered windows with windows with one-way glass
Planning, design, and construction $ 200,000
(18) Lahaina bypass, phase I, Maui
Lahainaluna road to Keawe Street extension, two lane "mini" bypass
Construction $30,000,000
(19) Honoapiilani highway, Maui
Widening of Honoapiilani highway from Lahaina to Maalaea
Planning $ 2,500,000
(20) Honoapiilani highway, Maui
Passing lanes
Design $ 1,500,000
SECTION 2. The bonds issued for the respective capital projects authorized under this Act shall not lapse at the end of the fiscal biennium for which the issuance is made; provided that all issuances which are unencumbered as of June 30, 2006, shall lapse as of that date.
SECTION 3. This Act shall take effect on July 1, 2003.
INTRODUCED BY: |