BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2003-2004.
1. To be expended by the department of accounting and general services:
A. President George Washington middle school, Oahu
Design and construction to replace bell system.
Design $ 20,000
Construction 150,000
Total funding 170,000
B. President George Washington middle school, Oahu
Equipment and installation to upgrade the telephone system.
Equipment $ 24,373
Installation 6,462
Total funding 30,835
C. President George Washington middle school, Oahu
Planning, design, construction, and equipment to replace the public address system.
Planning $ 840
Design 2,420
Construction 22,540
Equipment 19,640
Total funding 45,440
D. Hokulani elementary school, Oahu
Upgrade of electrical supply to all buildings.
Installation $ 200,000
Total funding 200,000
E. Lunalilo elementary school, Oahu
Design and construction of an air conditioning system for the computer room.
Design $ 3,000
Construction 17,000
Total funding 20,000
F. Lunalilo elementary school, Oahu
Upgrade electrical capacity.
Installation $ 300,000
Total funding 300,000
G. Lunalilo elementary school, Oahu
Installation of ceiling fans in classrooms in building A.
Installation $ 15,000
Total funding 15,000
H. Lunalilo elementary school, Oahu
Extension of a concrete wall fronting building A.
Construction $ 80,000
Total funding 80,000
I. Lunalilo elementary school, Oahu
Installation of security screens to windows of buildings A, C, and D.
Installation $ 24,000
Total funding 24,000
J. Prince Jonah Kuhio elementary school, Oahu
Design and construction of a second floor connecting the administration and library buildings.
Design $ 200,000
Construction 700,000
Total funding 900,000