Report Title:
CIP; 25th District
Description:
Appropriates moneys for capital improvement projects for the benefit of the 25th representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
2766 |
TWENTY-SECOND LEGISLATURE, 2004 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the twenty-fifth representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2004-2005:
1. To be expended by the department of accounting and general services:
A. Roosevelt high school, Oahu
Design and construction for access ramps at the drop-off and school evacuation areas, and leading to the bleachers and other locations around the stadium.
Design $1,000
Construction $29,000
Total funding $30,000
B. Roosevelt high school, Oahu
Design and construction for security fences around the rear of the campus.
Design $1,000
Construction $49,000
Total funding $50,000
C. Roosevelt high school, Oahu
Design and construction for an air conditioning system for building A.
Design $1,000
Construction $749,000
Total funding $750,000
D. Roosevelt high school, Oahu
Design and construction for improvements to the multi-purpose patio fronting building A.
Design $1,000
Construction $39,000
Total funding $40,000
E. Roosevelt high school, Oahu
Design and construction for a multi-athletic track complex in the stadium.
Design $1,000
Construction $2,499,000
Total funding $2,500,000
F. Stevenson middle school, Oahu
Design and construction for a retaining wall at Auwaiolimu street.
Design $1,000
Construction $499,000
Total funding $500,000
G. Stevenson middle school, Oahu
Design and construction for campus safety and walkway improvements.
Design $1,000
Construction $79,000
Total funding $80,000
H. Stevenson middle school, Oahu
Design and construction to repair road and fill potholes.
Design $1,000
Construction $74,000
Total funding $75,000
I. Stevenson middle school, Oahu
Design and construction to refinish stage.
Design $1,000
Construction $8,000
Total funding $9,000
J. Stevenson middle school, Oahu
Design and construction to renovate administrative offices, including air conditioning installation and additional office and storage space.
Design $1,000
Construction $209,000
Total funding $210,000
K. Stevenson middle school, Oahu
Design and construction for new fencing by the tennis court.
Design $1,000
Construction $49,000
Total funding $50,000
L. Stevenson middle school, Oahu
Design and construction for new cafeteria tables.
Design $1,000
Construction $15,000
Total funding $16,000
M. Makiki library/community center, Oahu
Design and construction for renovations to the library building.
Design $1,000
Construction $4,999,000
Total funding $5,000,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2004.
INTRODUCED BY: |
_____________________________ |