Report Title:
CIP; 22nd Representative District
Description:
Appropriates funds for capital improvement projects for the 22nd representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
1995 |
TWENTY-SECOND LEGISLATURE, 2004 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
MAKING APPROPRIATIONS FOR capital improvement projects for the TWENTY-SECOND representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2004-2005.
1. Hokulani elementary school, Oahu
Design and construction covered lanai around administration building to outlying buildings. Cover drop off/pick up area fronting E/administration to D/multi-purpose building. Cover ewa end of E/Administration to Building A. Extend cover makai end of E/Administration to Building G.
Plans $
Design
Construction
Equipment
Total Funding $
2. President George Washington middle school, Oahu
Planning, design, construction, and equipment to replace the public address system.
Plans $ 2,500
Design 2,500
Construction 25,000
Equipment 15,000
Total Funding $45,000
3. Ala Wai elementary school, Oahu
Planning, design, construction, and equipment to resurface parking lot 101.
Plans $
Design
Construction
Equipment
Total Funding $67,000
4. Ala Wai elementary school, Oahu
Planning, design, construction, and equipment to install permanent fencing and gates for the entire campus.
Plans $
Design
Construction
Equipment
Total Funding $25,000
5. Ala Wai elementary school, Oahu
Planning, design, construction, and equipment to reroof the cafeteria at Building G.
Plans $
Design
Construction
Equipment
Total Funding $92,000
6. Ala Wai elementary school, Oahu
Planning, design, construction, and equipment to reroof the library at Building F.
Plans $
Design
Construction
Equipment
Total Funding $50,000
7. Prince Jonah Kuhio elementary school, Oahu
Design and construction of a second floor connecting the administration and library buildings.
Design $200,000
Construction 700,000
Total Funding $900,000
8. King William C. Lunalilo elementary school, Oahu
Planning, design, construction, and equipment to reroof Building H.
Plans $
Design
Construction
Equipment
Total Funding $140,000
9. King William C. Lunalilo elementary school, Oahu
Planning, design, construction, and equipment to upgrade the fire alarm system.
Plans $
Design
Construction
Equipment
Total Funding $150,000
10. King William C. Lunalilo elementary school, Oahu
Replacement of furniture.
Equipment $6,000
Total Funding $6,000
11. King William C. Lunalilo elementary school, Oahu
Install security screens at Building A.
Equipment $30,000
Total Funding $30,000
12. King William C. Lunalilo elementary school, Oahu
Install security screens at Building C.
Equipment $30,000
Total Funding $30,000
13. King William C. Lunalilo elementary school, Oahu
Planning, design, construction, and equipment to reroof Building D.
Plans $
Design
Construction
Equipment
Total Funding $60,000
14. King William C. Lunalilo elementary school, Oahu
Planning, design, construction, and equipment to reroof Building E.
Plans $
Design
Construction
Equipment
Total Funding $125,000
15. King William C. Lunalilo elementary school, Oahu
classroom renovations
Plans $
Design
Construction
Equipment
Total Funding $1,360,000
16. King William C. Lunalilo elementary school, Oahu,
Electrical upgrade of the entire school
Plans $
Design
Construction
Equipment
Total Funding $300,000
SECTION 2. The sums appropriated shall be expended by the department of accounting and general services.
SECTION 3. This Act shall take effect on July 1, 2004.
INTRODUCED BY: |
_____________________________ |