A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the forty-second representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2003-2004.
1. To be expended by the department of accounting and general services:
A. Ewa elementary school
Electrical upgrade, lights in parking lot, window replacement, air conditioning.
Design $ 450,000
Construction 3,250,000
Total Funding $ 3,700,000
B. Campbell high school
Electrical upgrade, air conditioning.
Design $ 1,900,000
Construction 18,250,000
Total Funding $20,150,000
C. Waipahu intermediate school
Additional classroom buildings, extension of library parking lot.
Design $ 115,000
Construction 3,280,000
Equipment 100,000
Total Funding $ 3,495,000
D. Waipahu high school
1. Replacement of air conditioning unit.
Plans $ 4,000
Construction 100,000
Equipment 120,000
Total Funding $ 224,000
2. Replacement of fence surrounding school.
Plans $ 1,000
Construction 12,000
Equipment 9,000
Total Funding $ 22,000
E. Ewa beach elementary school
1. Conversion of kitchen and dining hall into classrooms and office space, equipment, ground and site improvements.
Design $ 25,000
Construction 225,000
Total Funding $ 250,000
2. Reinforcement of building support column.
Design $ 150,000
Construction 950,000
Total Funding $ 1,100,000
3. Air conditioning school-wide.
Design $ 500,000
Construction 4,500,000
Total Funding $ 5,000,000
F. Ilima intermediate school
1. Air conditioning school-wide.
Design $ 750,000
Construction 7,500,000
Total Funding $ 8,250,000
2. Automatic sprinkling system.
Design $ 31,000
Construction 245,000
Total Funding $ 276,000
G. Pohakea elementary school
1. Air conditioning school-wide.
Design $ 700,000
Construction 6,000,000
Total Funding $ 6,700,000
2. Automated sprinkler system.
Design $ 50,000
Construction 450,000
Total Funding $ 500,000
2. To be expended by the department of transportation:
A. Kapolei parkway
Planning, design, and construction of parkway extension.
Total Funding $
B. Kamokila boulevard
Extension of boulevard.
Total Funding $
C. North south road
Phases I and II from Kapolei parkway to H-1 freeway.
Total Funding $
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2003.