Report Title:

CIP; 29th Representative District

Description:

Appropriates funds for capital improvement projects for the benefit of the 29th representative district.

HOUSE OF REPRESENTATIVES

H.B. NO.

1432

TWENTY-SECOND LEGISLATURE, 2003

 

STATE OF HAWAII

 


 

A BILL FOR AN ACT

 

relating to capital improvement projects for the benefit of the twenty-ninth representative district.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2003-2004:

1. To be expended by the department of accounting and general services:

A. Farrington high school, Oahu

Design and construction to widen the Kalihi street entrance to accommodate large service trucks, school buses, and large numbers of students.

Design $45,000

Construction $200,000

Total funding $245,000

B. Farrington high school, Oahu

Design and construction to resurface Vance drive from the gym to Kalihi street and parking areas by shop U and the cafeteria.

Design $45,000

Construction $200,000

Total funding $245,000

C. Farrington high school, Oahu

Design and construction for the renovation of building R.

Design $50,000

Construction $457,000

Total funding $507,000

D. Farrington high school, Oahu

Design and construction for the renovation and reroofing of building O.

Design $75,000

Construction $800,000

Total funding $875,000

E. Fern elementary school, Oahu

Design and construction to resurface and upgrade electrical box in building B that services six classrooms.

Design $1,000

Construction $34,000

Total funding $35,000

F. Fern elementary school, Oahu

Design and construction to reroof building C.

Design $1,000

Construction $24,000

Total funding $25,000

G. Fern elementary school, Oahu

Design and construction to replace non-skid strips in six buildings.

Design $1,000

Construction $9,000

Total funding $10,000

H. Fern elementary school, Oahu

Design and construction to replace urinals in the boys' restroom.

Design $1,000

Construction $2,000

Total funding $3,000

I. Kalihi-Waena elementary school, Oahu

Design and construction to install air conditioning in the library.

Design $25,000

Construction $250,000

Total funding $275,000

J. Kalihi-Waena elementary school, Oahu

Design and construction to reroof buildings A and B.

Design $25,000

Construction $260,000

Total funding $285,000

K. Kalihi-Waena elementary school, Oahu

Design and construction to reroof building D.

Design $10,000

Construction $60,000

Total funding $70,000

L. Kalihi-Waena elementary school, Oahu

Design and construction to upgrade school electrical wiring capacity.

Design $25,000

Construction $225,000

Total funding $250,000

M. Kapalama elementary school, Oahu

Design and construction to resurface and restripe the basketball court.

Design $5,000

Construction $45,000

Total funding $50,000

N. Kapalama elementary school, Oahu

Design and construction for expansion, paving, and restriping the front parking lot.

Design $15,000

Construction $135,000

Total funding $150,000

O. Linapuni school, Oahu

Design and construction to install a covered walkway from building A to the cafeteria.

Design $5,000

Construction $30,000

Total funding $35,000

P. Linapuni school, Oahu

Design, construction, and equipment for a playcourt for the kindergarten through second-grade students.

Design $5,000

Construction $15,000

Equipment $50,000

Total funding $70,000

Q. Linapuni school, Oahu

Design and construction to install air conditioning in the computer room.

Design $25,000

Construction $225,000

Total funding $250,000

R. Puuhale school, Oahu

Design and construction to install a covered walkway from building A to the cafeteria.

Design $5,000

Construction $35,000

Total funding $40,000

S. Puuhale school, Oahu

Design and construction to install security window screens for eight glass windows.

Design $5,000

Construction $25,000

Total funding $30,000

T. Puuhale school, Oahu

Design and construction to resurface a parking lot.

Design $5,000

Construction $85,000

Total funding $90,000

U. Puuhale school, Oahu

Design and construction for a school roadway.

Design $5,000

Construction $75,000

Total funding $80,000

SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

SECTION 3. This Act shall take effect on July 1, 2003.

INTRODUCED BY:

_____________________________