relating to capital improvement projects for the benefit of the forty-third representative district.

 

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:

 


SECTION 1.  The following sums or so much thereof as shall be sufficient to finance the projects listed in this Act are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2009-2010:

1.   To be expended by the department of education:

A.   James Campbell high school, Oahu

     Design, construction, and equipment for a new classroom building.

     Design                                $1,230,000

     Construction                         $19,640,000

     Equipment                               $130,000

     Total funding                        $21,000,000

B.   James Campbell high school, Oahu

     Design, construction, and equipment for air-conditioning for the entire school.

     Design                                  $600,000

     Construction                         $10,400,000

     Equipment                             $1,000,000

     Total funding                        $12,000,000

C.   James Campbell high school, Oahu

     Plans for an athletic complex.

     Plans                                   $250,000

     Total funding                           $250,000

D.   James Campbell high school, Oahu

     Design and construction for electrical upgrades.

     Design                                   $85,000

     Construction                            $900,000

     Total funding                           $985,000

E.   Ewa elementary school, Oahu

     Design, construction, and equipment for a new classroom building.

     Design                                  $550,000

     Construction                          $7,350,000

     Equipment                               $100,000

     Total funding                         $8,000,000

F.   Ewa elementary school, Oahu

     Design and construction of playground equipment.


     Design                                   $10,000

     Construction                             $50,000

     Total funding                            $60,000

G.   Ewa elementary school, Oahu

     Plans, design, and construction for a parking lot.

     Plans                                    $50,000

     Design                                   $50,000

     Construction                          $1,000,000

     Total funding                         $1,100,000

H.   Ewa elementary school, Oahu

     Design, construction, and equipment for an eight- classroom building.

     Design                                  $700,000

     Construction                          $9,500,000

     Equipment                               $100,000

     Total funding                        $10,300,000

I.   Ewa elementary school, Oahu

     Design, construction, and equipment for air conditioning in buildings C and D.

     Design                                   $65,000

     Construction                            $500,000


     Equipment                                 $1,000

     Total funding                           $566,000

J.   Ewa Beach elementary school, Oahu

     Design, construction, and equipment for air conditioning in all classrooms.

     Design                                  $220,000

     Construction                          $3,280,000

     Equipment                               $500,000

     Total funding                         $4,000,000

K.   Ewa Beach elementary school, Oahu

     Design and construction for electrical upgrades to the school.

     Design                                   $60,000

     Construction                            $575,000

     Total funding                           $635,000

L.   Ilima intermediate school, Oahu

     Design and construction for air-conditioning of all classrooms and the administration building.

     Design                                  $600,000

     Construction                          $9,680,000

     Total funding                        $10,280,000

M.   Ilima intermediate school, Oahu

     Design, construction, and equipment for renovation and expansion of the library.

     Design                                  $570,000

     Construction                          $5,320,000

     Equipment                                $50,000

     Total funding                         $5,940,000

N.   Ilima intermediate school, Oahu

     Design and construction for replacement and installation of the public address system.

     Design                                   $35,000

     Construction                            $280,000

     Total funding                           $315,000

O.   Ilima intermediate school, Oahu

     Design and construction to enlarge and expand school parking lots.

     Design                                   $55,000

     Construction                            $600,000

     Total funding                           $655,000

P.   Ilima intermediate school, Oahu

     Design and construction for air-conditioning for all classrooms and administration building.

     Design                                  $600,000

     Construction                          $7,000,000

     Total funding                         $7,600,000

Q.   Ilima intermediate school, Oahu

     Design, construction, and equipment for two portable classrooms.

     Design                                   $50,000

     Construction                            $600,000

     Equipment                                $25,000

     Total funding                           $675,000

R.   Ilima intermediate school, Oahu

     Design and construction for electrical and technology network upgrades.

     Design                                  $175,000

     Construction                          $1,900,000

     Total funding                         $2,075,000

S.   Iroquois Point elementary school, Oahu

     Design and construction for a volleyball court.

     Design                                   $40,000

     Construction                            $230,000

     Total funding                           $270,000

T.   Iroquois Point elementary school, Oahu

     Design and construction for a grass field with sprinkler system.

     Design                                   $40,000

     Construction                            $340,000

     Total funding                           $380,000

U.   Kaimiloa elementary school, Oahu

     Design, construction, and equipment for a classroom building.

     Design                                  $700,000

     Construction                          $7,500,000

     Equipment                                $50,000

     Total funding                         $8,250,000

V.   Kaimiloa elementary school, Oahu

     Design, construction, and equipment for air conditioning for the entire school.

     Design                                  $470,000

     Construction                          $4,959,000

     Equipment                                 $1,000

     Total funding                         $5,430,000

W.   Keoneula elementary school, Oahu

     Design, construction, and equipment for a classroom building.

     Design                                  $700,000

     Construction                          $9,500,000

     Equipment                               $100,000

     Total funding                        $10,300,000

X.   Keoneula elementary school, Oahu

     Design, construction, and equipment for four portable classrooms.

     Design                                   $75,000

     Construction                          $1,100,000

     Equipment                                $40,000

     Total funding                         $1,215,000

 Y.  Keoneula elementary school, Oahu

     Design and construction for installation of gutters on all buildings.

     Design                                   $10,000

     Construction                            $100,000

     Total funding                           $110,000

Z.   Pohakea elementary school, Oahu

     Design, construction, and equipment for air conditioning and electrical system upgrades.

     Design                                   $80,000

     Construction                            $600,000

     Equipment                                 $1,000

     Total funding                           $681,000

AA.  Waipahu high school, Oahu

     Plans, design, and construction to complete fencing project.

     Plans                                     $1,000

     Design                                    $1,000

     Construction                             $73,000

     Total funding                            $75,000

BB.  Waipahu high school, Oahu

     Plans, design, and construction for the carpeting of the band room.

     Plans                                     $1,000

     Design                                    $1,000

     Construction                             $28,000

     Total funding                            $30,000

CC.  Waipahu high school, Oahu

     Plans, design, and construction for electrical upgrades to buildings H, G, and Q.

     Plans                                     $1,000

     Design                                    $1,000

     Construction                             $58,000

     Total funding                            $60,000

DD.  Waipahu intermediate school, Oahu

     Design and construction for telecommunications and electrical system upgrades.

     Design                                  $140,000

     Construction                          $1,200,000

     Total funding                         $1,340,000

EE.  Waipahu intermediate school, Oahu

     Design and construction for additional parking stalls to ease traffic flow into Waikele road.

     Design                                   $30,000

     Construction                            $450,000

     Total funding                           $480,000

FF.  Waipahu intermediate school, Oahu

     Design and construction for a fence along the back of the campus.

     Design                                   $10,000

     Construction                             $90,000

     Total funding                           $100,000

2.   To be expended by the University of Hawaii:

A.   University of Hawaii-West Oahu, Oahu

     Plans, design, and construction for an east-west connector road.

     Plans                                   $500,000

     Design                                $1,500,000

     Construction                         $10,000,000

     Total funding                        $12,000,000

3.   To be expended by the department of transportation:

A.   Ocean pointe marina, Oahu

     Land acquisition and construction for an intra-island ferry.

     Land                                 $10,000,000

     Construction                         $10,000,000

     Total funding                        $20,000,000

B.   North-south road, Oahu

     Design and construction for widening of the north south road from four lanes to six lanes.

     Design                                    $1,000

     Construction                         $19,999,000

     Total funding                        $20,000,000

C.   Fort Weaver road, Oahu

     Plans, design, and construction for road improvements for the area fronting the state child and family services complex and extending to old Fort Weaver road.

     Plans                                    $25,000

     Design                                  $250,000

     Construction                          $5,000,000

     Total funding                         $5,275,000

D.   Keaunui drive, Oahu

     Plans, design, and construction to extend the road to Renton road.

     Plans                                    $10,000

     Design                                   $50,000

     Construction                            $250,000

     Total funding                           $310,000

E.   Renton road and Roosevelt avenue, Oahu

     Plans, design, and construction to add a street light at the intersection.

     Plans                                     $1,000

     Design                                    $1,000

     Construction                             $10,000

     Total funding                            $12,000

G.   Leeward bikeway, Oahu

     Plans, land acquisition, design, and construction for phases one and two.

     Plans                                   $100,000

     Land                                 $10,000,000

     Design                                $2,000,000

     Construction                         $13,000,000

     Total funding                        $25,100,000

H.   Kunia Road, Oahu

     Plans, design, and construction to extend 3rd lane over Farrington Highway to the H-1 Freeway.

     Total Funding                        $40,000,000

     SECTION 2.  The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.

SECTION 3.  The following sums, or so much thereof as may be necessary for fiscal year 2009-2010 are appropriated or authorized, as the case may be, from moneys in the treasury received from federal grants and revenue bond funds to finance the following project on Oahu.  The letter symbols used after the specific project appropriations indicate the source of financing and have the following meaning: (E) revenue bond funds, and ( ) federal funds.

North–south road, Oahu 

Construction of north-south road from Kapolei parkway to Keoneula Boulevard.              $7,000,000(E)

                                       $28,000,000( )

The sums appropriated shall be expended, and the bonds authorized shall be issued, by the department of transportation for the purposes of this section.  Any unexpended or unencumbered balance of any appropriation made by this Act as of the close of business on June 30, 2012, shall lapse into the fund from which appropriated.  Any unissued balance of any authorization made by this section as of the close of business on June 30, 2012, shall lapse.

SECTION 4.  The following sums, or so much thereof as may be necessary for fiscal year 2009-2010 are appropriated or authorized, as the case may be, from moneys in the treasury received from special funds and the general obligation bond fund to finance the following project on Oahu.  The letter symbols used after the specific project appropriations indicate the source of financing and have the following meaning: (B) special funds, (C) general obligation bond fund.

University of Hawaii West Oahu campus, Oahu

Development of a West Oahu campus.    $100,000,000(B)

                                      $ 35,000,000(C)

     The sums appropriated shall be expended, and the bonds authorized shall be issued, by the University of Hawaii for the purposes of this section.  Any unexpended or unencumbered balance of any appropriation made by this Act as of the close of business on June 30, 2012, shall lapse into the fund from which appropriated.  Any unissued balance of any authorization made by this section as of the close of business on June 30, 2012, shall lapse.

     SECTION 5.  This Act shall take effect on July 1, 2009.

 

 