Report Title:
CIP; 31st Representative District
Description:
Appropriates funds for capital improvement projects for the benefit of the 31st representative district.
HOUSE OF REPRESENTATIVES |
H.B. NO. |
1992 |
TWENTY-SECOND LEGISLATURE, 2004 |
||
STATE OF HAWAII |
||
|
A BILL FOR AN ACT
relating to capital improvement projects for the benefit of the thirty-first representative district.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF HAWAII:
SECTION 1. The following sums, or so much thereof as shall be sufficient to finance the projects listed in this Act, are hereby appropriated out of the general revenues of the State of Hawaii for fiscal year 2004-2005:
1. To be expended by the department of accounting and general services:
A. Aliamanu elementary school, Oahu
Design and construction of a security fence around the perimeter of the school.
Design $5,000
Construction $75,000
Total funding $80,000
B. Aliamanu elementary school, Oahu
Plans, design, and construction for a new classroom building.
Plans $30,000
Design $70,000
Construction $1,200,000
Total funding $1,300,000
C. Aliamanu elementary school, Oahu
Plans, design, and construction for a new administrative office.
Plans $30,000
Design $70,000
Construction $1,200,000
Total funding $1,300,000
D. Aliamanu elementary school, Oahu
Plans, design, and construction for a new library and computer laboratory building.
Plans $30,000
Design $70,000
Construction $1,400,000
Total funding $1,500,000
E. Aliamanu middle school, Oahu
Design and construction for electrical upgrades.
Design $20,000
Construction $330,000
Total funding $350,000
F. Aliamanu middle school, Oahu
Design and construction to repair deteriorated volleyball and basketball courts.
Design $20,000
Construction $220,000
Total funding $240,000
G. Moanalua elementary school, Oahu
Plans, design, and construction to expand the existing library building to accommodate a video-media production center.
Plans $5,000
Design $15,000
Construction $280,000
Total funding $300,000
H. Moanalua elementary school, Oahu
Plans, design, and construction for an eight-classroom building.
Plans $20,000
Design $80,000
Construction $3,900,000
Total funding $4,000,000
I. Moanalua middle school, Oahu
Design and construction for electrical upgrades throughout the school.
Design $20,000
Construction $134,000
Total funding $154,000
J. Salt Lake elementary school, Oahu
Design and construction to renovate building C to create more classrooms and self-contained classrooms.
Design $85,000
Construction $665,000
Total funding $750,000
SECTION 2. The sums appropriated for the respective capital projects set forth in section 1 shall be expended by the designated expending agency for the purposes of this Act.
SECTION 3. This Act shall take effect on July 1, 2004.
INTRODUCED BY: |
_____________________________ |